Print Back to Calendar Return
  County Administrator's Report     10. 4.    
BCC Regular Meeting Discussion  
Meeting Date: 05/16/2019  
Issue:    Acquisition of Real Property located at 416 and 450 Herman Street for the Delano/Herman Streets Drainage Improvement Project
From: Joy Jones
Department: Engineering  
CAO Approval:

RECOMMENDATION:
Recommendation Concerning Acquisition of Real Property Located at 416 and 450 West Herman Street for the Delano/Herman Streets Drainage Improvement Project - Joy Jones, P.E., Engineering Department Director

That the Board take the following action regarding the acquisition of real property (approximately 2.15 acres) located at 416 and 450 West Herman Street from Rocky's Collision Center, Inc.: 

A. Authorize the purchase of three parcels of real property located at 416 and 450 West Herman Street (approximately 2.15 acres), owned by Rocky's Collision Center, Inc., for the Delano/Herman Streets Drainage Improvement Project, for an average of the County's appraised values of $820,000 and $870,000, which equals $845,000, in accordance with the terms and conditions contained in the Contract for Sale and Purchase;

B. Approve the Contract for Sale and Purchase for the acquisition of three parcels of real property located at 416 and 450 West Herman Street (approximately 2.15 acres) from Rocky's Collision Center, Inc., for $845,000; and

C. Authorize the County Attorney's Office to prepare, and the Chairman or Vice Chairman to execute any documents, subject to Legal review and sign-off, necessary to complete the acquisition of this property, without further action of the Board.

[Funding Source:  Fund 352, LOST III/HMGP Grant, Cost Center 210124, Object Code 56101, Project 17EN3743. Funds spent toward this project are eligible for reimbursement through the Hazard Mitigation Grant Program]

These properties are located in District 3.
BACKGROUND:
Escambia County has a long history of stormwater drainage problems and frequent flooding in the Pace Boulevard/Herman Street/Fairfield Street/Delano Street areas impacting government buildings, private facilities and roadways. These parcels will be used to expand the adjacent stormwater pond.

Following the April 2014 Flood Event, the Florida Department of Emergency Management (FDEM) approved funding for the design of a project to mitigate flooding in the Delano Street area. The design for the Delano Area Drainage Project has been completed, permitted, and submitted to FDEM for approval of grant funding for acquisition and construction.

The closings for all properties within the Delano Area Drainage Project will be scheduled once FDEM has approved acquisition and construction funding. This property owner is aware the closing will be delayed until then to comply with grant reimbursement requirements. 
BUDGETARY IMPACT:

Funding for this project is available in Fund 352, LOST III/HMGP Grant, Cost Center 210124, Object Code 56101, Project 17EN3743. Funds spent toward this project are eligible for reimbursement through the Hazard Mitigation Grant Program.

LEGAL CONSIDERATIONS/SIGN-OFF:
The County Attorney's Office will prepare the closing documents and conduct the closing for the purchase of this property.  The Contract for Sale and Purchase was approved as to form and legal sufficiency by Stephen West, Assistant County Attorney, on April 18, 2019.
PERSONNEL:
All work associated with this request is being done in-house and no additional staff is required.
POLICY/REQUIREMENT FOR BOARD ACTION:
These actions are consistent with the provisions of Section 46-139 of the Escambia County Code of Ordinances.
IMPLEMENTATION/COORDINATION:
Upon Board approval, staff will maintain compliance with Section 46-139 of the County Codes.

Attachments
Rocky's Contract
Rocky's Public Disclosure of Interest
Appraisal Summary Rocky's_McKenney
Appraisal Summary Rocky's_Asmar
Map Rocky's Collision Delano Drainage