Print Back to Calendar Return
  County Administrator's Report     17. 8.    
BCC Regular Meeting Budget & Finance Consent  
Meeting Date: 07/19/2016  
Issue:    Contract Award for Montclair Sidewalks & Resurfacing Phase 1 - Havre Way
From: Claudia Simmons
Department: Asst County Administrator  
CAO Approval:

RECOMMENDATION:
Recommendation Concerning Contract Award for Montclair Sidewalks & Resurfacing Phase 1, Havre Way - Claudia Simmons, Office of Purchasing, Purchasing Manager

That the Board approve and authorize the County Administrator to sign the Agreement between Escambia County, Florida, and Roads, Inc. of NWF, per the terms and conditions of PD 15-16.059, Montclair Sidewalks & Resurfacing Phase 1 - Havre Way, in the amount of $429,636.74.

[Funding Source:  Fund 352, LOST III, Account 210107/56301/Project #08EN0208 (Resurfacing) - $160,009.84;
Fund 352, LOST III, Account 210107/56301/Project #16EN3415 (Montclair SW) - $208,080.00;
Fund 352, LOST III, Account 210107/56301/Project #12EN1738 (NIP) - $24,733.45;
Fund 181, Master Drainage Basin Fund 12, Account 210730/56301 - $12,000.00; and
Fund 151, Community Redevelopment (TIF), Account 370115/56301 - $24,813.45.
Total Funding = $429,636.74]
BACKGROUND:
The Montclair Sidewalks & Resurfacing Phase I – Havre Way project consists of the construction of sidewalks on the west side of Havre Way, resurfacing Havre Way along the sidewalk improvement area, driveway replacement, and other items needed to support this improvement.  The proposed improvements will be constructed within the existing Escambia County rights-of-way and/or on any proposed temporary work agreements secured.  Construction is scheduled to start early August 2016.

The legal Advertisement for this "Invitation to Bid" was advertised in the Pensacola News Journal in Monday, May 30, 2016 and Monday, June 06, 2016. A Non-Mandatory Pre-Solicitation Conference was held on Wednesday, June 08, 2016. Four firms were represented at that meeting. Bids were received from five firms on Thursday, June 23, 2016. Roads, Inc of NWF is the lowest bidder.
BUDGETARY IMPACT:
Funding  Source:
Fund 352, LOST III, Account 210107/56301/Project #08EN0208 (Resurfacing)
$160,009.84
Fund 352, LOST III, Account 210107/56301/Project #16EN3415 (Montclair SW)
$208,080.00
Fund 352, LOST III, Account 210107/56301/Project #12EN1738 (NIP)
$24,733.45
Fund 181, Master Drainage Basin Fund 12, Account 210730/56301
$12,000.00
Fund 151, Community Redevelopment (TIF), Account 370115/56301
$24,813.45
Total Funding  $429,636.74
LEGAL CONSIDERATIONS/SIGN-OFF:

Attorney Standard Form of Contract, Form D: Road/Drainage.

PERSONNEL:
All work associated with this recommendation was done in-house and no additional staff was required.
POLICY/REQUIREMENT FOR BOARD ACTION:
This recommendation is in compliance with the Code of Ordinances of Escambia County, Fl 1999, Chapter 46, Finance, Article II Purchases and Contracts.

The Montclair Sidewalks & Resurfacing Phase I – Havre Way project consists of the construction of sidewalks on the west side of Havre Way, resurfacing Havre Way along the sidewalk improvement area, driveway replacement, and other items needed to support this improvement.  The proposed improvements will be constructed within the existing Escambia County rights-of-way and/or on any proposed temporary work agreements secured.  Construction is scheduled to start early August 2016.

The legal Advertisement for this "Invitation to Bid" was advertised in the Pensacola News Journal in Monday, May 30, 2016 and Monday, June 06, 2016. A Non-Mandatory Pre-Solicitation Conference was held on Wednesday, June 08, 2016. Four firms were represented at that meeting. Bids were received from five firms on Thursday, June 23, 2016. Roads, Inc of NWF is the lowest bidder.
IMPLEMENTATION/COORDINATION:

The Office of Purchasing will issue the Attorney's Standard Form of Contract Form D: Road/Drainage and PO.


Attachments
Agreement
Bid Tab

AgendaQuick©2005 - 2024 Destiny Software Inc., All Rights Reserved