  County Administrator's Report     12. 15.    
BCC Regular Meeting Budget & Finance Consent  
Meeting Date: 05/21/2015  
Issue:    Acceptance of Five Easements For Crescent Lake Dam Restoration Project
From: Joy D. Blackmon, P.E.
Department: Public Works  
CAO Approval:

RECOMMENDATION:
Recommendation Concerning Acceptance of Five Easements for the Crescent Lake Dam Restoration Project - Joy D. Blackmon, P.E., Public Works Department Director

That the Board take the following action concerning acceptance of the donation of five easements located in the Crescent Lake area for dam restoration improvements:

A. Accept the donation of five easements located in the Crescent Lake area, from the following property owners, for dam restoration improvements:   
                              
                                           
Property Owner Parcel Reference Number Easement
1. Crescent Lake Preservation Association, Inc. 44-1S-30-3001-012-001 Stormwater Management Utility Easement
2. Sovran Acquisition Limited Partnership 44-1S-30-3001-000-000 Drainage & Access Easement
3. Sovran Acquisition Limited Partnership 44-1S-30-3001-000-000 Temporary Construction Easement
4. Michael E. and Judy L. Stephens 44-1S-30-3001-001-001 Drainage Easement
5. Michael E. and Judy L. Stephens 44-1S-30-3001-001-001 Temporary Construction Easement

B. Authorize the payment of documentary stamps because the properties are being donated for governmental use, which is for drainage improvements, and the County benefits from the acceptance of this property, which enhances the safety and well-being of the citizens of Escambia County;

C. Authorize the payment of incidental expenditures associated with the recording of documents; and

D. Authorize staff to prepare, and the Chairman or Vice Chairman to accept the Easements, subject to Legal review and sign-off, as of the day of delivery of the Easements to the Chairman or Vice Chairman, and authorize the Chairman or Vice Chairman to acknowledge the Board's acceptance at that time.

[Funding:  Funds for incidental expenses associated with recording of documents are available in an Engineering Escrow Account accessed by the Escambia County Clerk's Office]
BACKGROUND:
Crescent Lake Dam Restoration Project is part of the Natural Resources Conservation Service and Emergency Watershed Protection (NRCS - EWP) program. The April 2014 storm event caused the 72-acre lake embankment to overflow, which caused the dam to fail. The dam failure resulted in downstream flooding, which left large deposits sediments and debris. The proposed action from the NRCS is to repair the breach in the embankment and install a concrete emergency spillway structure. They intend to sod and vegetate all disturbed areas and remove debris and sediment from the downstream channel to Michigan Avenue to prevent future flooding.

This project, which will be completed in three phases, will impact three parcels or property. The drainage and access easements and the temporary construction easements are all vital for this project to move forward. Phase One, scheduled to begin in June 2015, will consist of de-watering. Phase Two, which will begin in July 2015, will focus on debris and sediment removal. The final phase, project construction, will begin in September 2015 and will conclude in October 2015.
BUDGETARY IMPACT:
Funds for incidental expenses associated with the recording of documents are available in an Engineering Escrow Account accessed by Escambia County Clerk's Office.
LEGAL CONSIDERATIONS/SIGN-OFF:
The Easements will be approved as to form and legal sufficiency by the County Attorney's office prior to execution by the Chairman.
PERSONNEL:
All work associated with this request is being done in-house and no additional staff is required.
POLICY/REQUIREMENT FOR BOARD ACTION:
These actions are consistent with the provisions of Section 46-139, Escambia County Code of Ordinances.
 
IMPLEMENTATION/COORDINATION:
Upon Board approval, staff will proceed in compliance with Section 46-139 of the County Code of Ordinances.

Attachments
Crescent Lake Preservation Association Stormwater Easement
Sovran Drainage & Access Easement
Sovran Temporary Construction Easement
Stephens_Drainage Easement
Stephens_Temporary Construction
Aerial Map