Print Back to Calendar Return
  County Administrator's Report     11. 6.    
BCC Regular Meeting Technical/Public Service Consent  
Meeting Date: 07/16/2020  
Issue:    Scheduling a Public Hearing Concerning Proposed Grant Application for Federal Transit Administration (FTA) 5339 Bus and Bus Facilities
From: TONYA ELLIS
Department: Mass Transit  
CAO Approval:

RECOMMENDATION:
Recommendation Concerning Scheduling a Public Hearing Concerning Proposed Grant Application for Federal Transit Administration (FTA) Bus and Bus Facilities Funding for Mass Transit Capital Projects - Tonya Ellis, Mass Transit Department Director

That the Board authorize the scheduling of a Public Hearing for August 6, 2020, at 5:33 p.m., for the purpose of receiving comments from the public concerning the Section 5339 proposed Grant Application by the Mass Transit Department, for Federal Transit Administration (FTA) Section 5339 Funds for Capital Projects.

[Funding: The Grant Application is for a total of $1,612,050.  The local Match of $403,013 will be covered by Federal Highway Toll Revenue Credits.]
BACKGROUND:
FTA guidelines require that all applications for financial assistance from FTA be submitted after a public hearing is held for the purpose of receiving comments from the public concerning the Grant Program of Projects.  Effective January 1, 2016, Grant Applications, Execution, and Grant Administration Progress Reports must be submitted electronically via the Transportation Award Management System (TrAMS).

The FTA Published apportionments under Section 5339, and this application includes funding for multiple financial years - FY17 through FY20 for a total of $1,612,050.  Mass Transit staff recommend that the Escambia County Board of County Commissioners apply for these apportionments by approving this Application for the below Program of Projects.
 
Budget Category Definition / Reasoning Project Cost
Bus Equipment and Facilities Acquisition of a Bus Vacuum Cleaning System - increase efficiencies in Maintenance / Bus Cleaning $300,000
  Acquire Shop Equipment - Hydraulic Press, Drill Press, Parts Washer, Exhaust Fans, Compressors $82,050
  Software / Technology - Fixed Route Scheduling Software $800,000
  Software / Technology - Paratransit Scheduling Software $180,000
  Software / Technology - Passenger Information $250,000
  TOTAL $1,612,050
BUDGETARY IMPACT:
The Grant Application is for a total of $1,612,050.  The local Match of $403,013 will be covered by Federal Highway Toll Revenue Credits.
LEGAL CONSIDERATIONS/SIGN-OFF:
N/A
PERSONNEL:
N/A
POLICY/REQUIREMENT FOR BOARD ACTION:
This Recommendation is based on the Board of County Commissioners Comprehensive Plan - Mobility Element.
IMPLEMENTATION/COORDINATION:
Mass Transit staff will electronically file all required documentation; and will coordinate with FTA for all necessary funding activities.

Attachments
Draft Application

AgendaQuick©2005 - 2024 Destiny Software Inc., All Rights Reserved