Issue:    Willowbrook Lake Dam Project
From: Joy Jones
Department: Public Works  
CAO Approval:

RECOMMENDATION:

Recommendation Concerning the Willowbrook Lake Dam Project - Joy Jones, P.E., Public Works Department Director


That the Board approve bringing $400,000, available in “Local Option Sales Tax” (LOST) IV, Cost Center 210106, Fund 353, forward from Fiscal Year 2020 to Fiscal Year 2019 for the Willowbrook Lake Dam project so that staff can begin the construction process. 

This project is located in Commission District 5.

BACKGROUND:

Willowbrook Lake is located south of Kingsfield Road, north of Ten Mile Road, east of US 29, west of Chemstrand Road, and serves as a storm water retention pond for this area.

 

The dam and outfall structure at Willowbrook Lake was severely damaged during the April 2014 Rainfall Event. The infrastructure of Chemstrand Road was also comprimised, a major corridor to industries north of Nine Mile Road. The purpose of this project is to reconstruct the dam to provide stormwater management and treatment for the area, protect the infrastructure of Chemstrand Road, reduce flooding for downstream properties and restore the original lake area

 

The project will include removing and rebuilding the dam with a solid clay core, an inlet system, and an energy dissipater. A concrete overflow weir will control the level of the lake during a storm. The project design has been completed and all permits have been acquired.

BUDGETARY IMPACT:
No budgetary impact occurs. Funding is currently available in Fund 353, "Local Option Sales Tax IV", Account 210106.
LEGAL CONSIDERATIONS/SIGN-OFF:
N/A
PERSONNEL:
N/A
POLICY/REQUIREMENT FOR BOARD ACTION:
Scheduling and prioritization of capital improvement projects is at the discretion of the Board.
IMPLEMENTATION/COORDINATION:
Upon Board approval of this request, a budget amendment will be forwarded to the Office of Management and Budget to reallocate the funds to the appropriate project.