  County Administrator's Report     10. 4.    
BCC Regular Meeting Discussion  
Meeting Date: 09/21/2017  
Issue:    Approve the Design Change Order for OLF-X Phase II Changes
From: Jack Brown
Department: County Administrator's Office  
CAO Approval:

RECOMMENDATION:
Recommendation Concerning Approving a Design Change Order at no Cost to the County for OLF-X Phase II Changes Based on the Proposed Alternative Resolution, as Provided by Baskerville-Donovan, Inc. - Jack R. Brown, County Administrator 

That the Board approve and authorize the County Administrator to sign a Design Change Order at no cost to the County for OLF-X Phase II Airfield Design Drawings and Specifications Changes, based on the following proposed alternative resolution, as provided by Baskerville-Donovan, Inc.:

A. Baskerville-Donovan, Inc., will provide the Phase II Airfield design revisions and updates as outlined in Exhibit "H" at no cost to the County;

B. The Board agrees to rescind its action for payment from Baskerville-Donovan, Inc., in the amount of $462,658.92, as outlined in the letter dated June 23, 3017;

C. The Board will allow Baskerville-Donovan, Inc., direct or indirect communication with the Navy to provide clarity regarding the design changes and updates listed in Exhibit "H";

D. Baskerville-Donovan, Inc., will not be held responsible for the Phase I Contractor's demobilization resulting in his inability to complete the project on-time, which may result in further damages, potential delays regarding a Land Swap with the Navy and County or impacts on any agreements for subsurface mineral rights associated with the project completion; and

E. Baskerville-Donovan, Inc., will maintain the Construction Engineering Inspection (CEI) services in their current contract for all Phases of OLF-X.
BACKGROUND:
On June 23, 2017, the County sent a demand letter to Baskerville-Donovan, Inc., requesting payment in the amount of $462,658.92 on the OLF-X project. On September 11, 2017, Baskerville-Donovan, Inc., sent a letter to the County with an alternative resolution to get the project moving forward.
BUDGETARY IMPACT:
Based on the alternative resolution proposed by Baskerville-Donovan, Inc., the Design Change Order will be executed at no cost the County.
LEGAL CONSIDERATIONS/SIGN-OFF:
The County Attorney's Office has been involved in all phases of the OLF-X property swap.
PERSONNEL:
NA
POLICY/REQUIREMENT FOR BOARD ACTION:
NA
IMPLEMENTATION/COORDINATION:
Upon Board approval, the County Administrator will sign the Change Order.

Attachments
Land Agreement for NOLF
Phase II Changes September 11, 2017 Baskerville-Dovonan, Inc.
Letter Date 06_23_17 to Baskerville-Donovan, Inc.
Change Order #2 for Purchase Order 151442-2