  County Administrator's Report     16. 13.    
BCC Regular Meeting Budget & Finance Consent  
Meeting Date: 04/06/2017  
Issue:    Change Order on Contract PD 11-12.030 "Beach Haven Northeast Drainage and Sanitary Sewer Project"
From: Joy D. Blackmon, P.E.
Department: Public Works  
CAO Approval:

RECOMMENDATION:
Recommendation Concerning a Change Order on Contract PD 11-12.030 for the Beach Haven Northeast Drainage and Sanitary Sewer Project - Joy D. Blackmon, P.E., Public Works Department Director

That the Board approve and authorize the County Administrator to execute the following Change Order on Contract PD 11-12.030 for the Beach Haven Northeast Drainage and Sanitary Sewer Project, to Jehle-Halstead, Inc.:
 
Department: Public Works
Division: Engineering
Type: Addition
Amount: $80,845
Vendor: Jehle-Halstead, Inc.
Project Name: Beach Haven Northeast Drainage and Sanitary Sewer Project
Contract: PD 11-12.030
PO No.: 121406
CO No.: 3
Original Award Amount: $999,430
Cumulative Amount of Change Orders through this CO: $99,845
New Contract Total: $1,099,275


[Funding Source:  Fund 352, LOST III, Cost Center 210107, Object Code 56301, Project #08EN0272.  This Change Order is for CEI services; Emerald Coast Utilities Authority (ECUA) will reimburse 40% of the cost]
BACKGROUND:
Meeting in regular session on July 12, 2012, the Board approved the Agreement with Jehle-Halstead, Inc., for Contract PD 11-12.030 for the Beach Haven Northeast Drainage and Sanitary Sewer Project.  

Currently, Beach Haven Northeast Phase I is under construction and Phase 2 is under design. Due to the size and complexity of the project, the Engineer of Record's (EOR) inspection services need to be increased over the two-year construction period so that their oversight will be sufficient to adequately provide as-built certification to permitting agencies as required. A cost agreement between Emerald Coast Utilities Authority (ECUA), who will pay 40%, and the County, who will pay 60%, exists to help offset design costs for both agencies. 

Change Order #1 extended the completion time to July 23, 2019. The new completion schedule is July 17, 2020, (360 days), to allow for Phase 2 construction and as-built certifications. Change Order #2 increased the cost of the contract by $19,000 to satisfy strict environmental criteria required by grant agencies. This Change Order, #3, requests additional funds, in the amount of $80,845, to compensate Jehle-Halstead, Inc., for limited construction administration and inspections tasks, attending onsite, County, and public meetings as needed, and assistance with the Phase 2 bid process. The new contract total will be $1,099,275.
BUDGETARY IMPACT:
Funding Source:  Fund 352, LOST III, Cost Center 210107, Object Code 56301, Project #08EN0272,  This change order is for CEI services, Emerald Coast Utilities Authority (ECUA) will reimburse 40% of the cost.
LEGAL CONSIDERATIONS/SIGN-OFF:
N/A
PERSONNEL:
N/A
POLICY/REQUIREMENT FOR BOARD ACTION:
This recommendation is in compliance with the provisions of the Code of Ordinances of Escambia County, Florida, Chapter 46, Finance, Article II, Purchase and Contracts.
IMPLEMENTATION/COORDINATION:
Upon approval of this recommendation, a Change Order will be transmitted to the Office of Purchasing for processing.

Attachments
Original PO with Agreement
Change Order 1
Change Order 2
Backup Change Order 3 Pending
Board Action 07/12/2012