  County Administrator's Report     13. 24.    
BCC Regular Meeting Budget & Finance Consent  
Meeting Date: 12/05/2019  
Issue:    Contract Award for PD 18-19.098 Bob Sikes Bridge Rehabilitation Project
From: PAUL NOBLES
Department: Asst County Administrator  
CAO Approval:

RECOMMENDATION:
Recommendation Concerning the Contract Award for PD 18-19.098, Bob Sikes Bridge Rehabilitation Project - Joy Jones, Department Director, Engineering; and Paul Nobles, Purchasing Manager, Office of Purchasing

That the Board approve and authorize the County Administrator to sign the Agreement between Escambia County, Florida, and Southern Road & Bridge, LLC, per the terms and conditions of PD 18-19.098, Bob Sikes Bridge Rehabilitation Project, for a lump sum of $4,297,269.

This solicitation was noticed on July 29, 2019, via Vendor Registry to 63 registrants representing 50 firms. The solicitation was viewed by 68 firms and downloaded by 49 firms.

[Funding:  Fund 167, Bob Sikes Toll Bridge; Cost Center 140302, Bob Sikes Toll Operation & Maintenance; Object Code 56301, Improvements Other Than Buildings - $4,000,000.00; and
Fund 352, Local Option Sales Tax (LOST) III; Cost Center 210107, Transportation & Drainage; Object Code 56301, Improvements Other Than Buildings; Project #20EN4244 - $297,269.00]

NON-ADA COMPLIANT DOCUMENTS TO BE DISTRIBUTED UNDER SEPARATE COVER
  • Original Solicitation
  • Bid Tab Under Review
  • Bid Response from Southern Road & Bridge, LLC
  • Bid Tab Recommendation to Award
  • Bid Distribution List
  • Bid Analytics
  • Determination to Award Checklist
  • Agreement
BACKGROUND:
The Bob Sikes Bridge Rehabilitation Project involves the West Bridge (480123) and East Bridge (480139), conveying vehicle and foot traffic on County Road 399 over the Santa Rosa Sound between the City of Gulf Breeze in Santa Rosa County, and Pensacola Beach in Escambia County, Florida. The total project length is 1620 lineal feet (0.19 miles). The improvements consist of deck and beam repairs, concrete repairs, cleaning and coating, joint replacement, fender improvements, fender cleaning and coating, bulkhead and rip-rap repairs, and installation of cathodic protection on structures. Rehabilitation is expected to extend the life of the bridges 12 years per design criteria, to 2036. Deck work and maintenance of traffic during rehabilitation will be scheduled to minimize impacts to beach season visitors.

This solicitation was noticed on July 29, 2019, via Vendor Registry to 63 registrants representing 50 firms. The solicitation was viewed by 68 firms and downloaded by 49 firms.

Two bids were received on September 5, 2019, with Southern Road & Bridge, LLC, being deemed the lowest responsive bidder with a bid of $4,297,269.
BUDGETARY IMPACT:
Funding:  Fund 167, Bob Sikes Toll Bridge; Cost Center 140302, Bob Sikes Toll Operation & Maintenance; Object Code 56301, Improvements Other Than Buildings - $4,000,000.00; and
Fund 352, Local Option Sales Tax (LOST) III; Cost Center 210107, Transportation & Drainage; Object Code 56301, Improvements Other Than Buildings; Project #20EN4244 - $297,269.00
LEGAL CONSIDERATIONS/SIGN-OFF:
Attorney's Standard Form of Agreement, Form B: Construction
PERSONNEL:
All work associated with this solicitation was performed in-house and no additional staff was required.
POLICY/REQUIREMENT FOR BOARD ACTION:
This Recommendation is in compliance with the Code of Ordinances of Escambia County, FL 1999, Chapter 46, Finance, Article II, Purchases and Contracts.
IMPLEMENTATION/COORDINATION:
The Office of Purchasing will issue the Agreement and the Purchase Order. The Escambia County Engineering Department will have administrative oversight of the project.