  County Administrator's Report     14. 37.    
BCC Regular Meeting Budget & Finance Consent  
Meeting Date: 12/06/2018  
Issue:    Contract Award for Automated Fuel Management System
From: Paul Nobles
Department: Asst County Administrator  
CAO Approval:

RECOMMENDATION:
Recommendation Concerning Automated Fuel Management System - Paul Nobles, Purchasing Manager, Office of Purchasing

That the Board take the following action:

A. Approve and authorize the County Administrator to sign the Agreement between Escambia County, Florida, and MECO, Inc. per the terms and conditions of PD 15-16.104, Automated Fuel Management System, based on a final and best offer of $424,308; and

B. Authorize the County Administrator to approve and execute any Owner-Direct Purchase Orders that exceed $50,000.

[Funding:  Fund 501, Fuel Distribution; Cost Center 210407, Fuel Distribution; Object Code 55201, Operating Supplies]
BACKGROUND:
The legal advertisement for this "Request For Proposals" was advertised in the Pensacola News Journal on September 19, 2016.  A mandatory pre-solicitation conference / location walk thru was held on October 3, 2016.  Seven firms were represent at that meeting.  Proposals were received from three contractors on October 26, 2016.  Two firms were short-listed on November 8, 2016:
MECO, Inc.
Guardian Fueling Technologies, LLC

Discussions were held with the following firms with the intent to determine a recommended firm on November 17, 2016.  Unfortunately, both firms exceeded the established budget and thus a recommendation could not be presented (budget $300,000).
MECO, Inc. $639,160.27
Guardian Fueling Technologies, LLC $771,298.26

A meeting was held on July 20, 2018 between the committee and the two short-listed firms to review the scope and determine whether modifications could be madethat could meet the budget without reducing the intended original scope.  After review and agreement with both firms, each firm was asked to provide their final and best offer.

MECO, Inc. is the lowest most responsive and responsible proposer.
BUDGETARY IMPACT:
[Funding: Fund 501, Fuel Distribution; Cost Center 210407, Fuel Distribution; Object Code 55201, Operating Supplies]
LEGAL CONSIDERATIONS/SIGN-OFF:
Attorney Standard Form of Contract, Form B: Construction
PERSONNEL:
N/A
POLICY/REQUIREMENT FOR BOARD ACTION:
This recommendation is in compliance with the Code of Ordinances of Escambia County, FL 1999, Chapter 46, Finance, Article II Purchases and Contracts.
IMPLEMENTATION/COORDINATION:
The Office of Purchasing will issue the Standard Form of Contract, Form B: Construction and Purchase Order.

Attachments
Register of Proposers
Original Solicitation
Revised Specifications 07/24/2018
Agreement
MECO Final and Best Offer
Guardian Fueling Technologies Final and Best Offer
Committee Evaluation Spreadsheet

AgendaQuick©2005 - 2024 Destiny Software Inc., All Rights Reserved